Crews are up against Mother Nature to finish repairs on the Highway 16 fly-over near SaskTel Centre.
The overpass which handles 7,800 vehicles a day has been closed since the end of June. The project which involved repaving the deck and concrete work was expected to be finished by late September to early October.
Joel Cherry with the Ministry of Highways and Infrastructure told the Brent Loucks Show Tuesday the project fell behind schedule after crews discovered the overpass was in far worse condition.
“When they got in there and chipped away at the concrete surface they saw the bridge was structurally in poorer condition than we first thought ,” said Cherry.
“It’s like you’re doing renovation on an older house. You pull out the tiles an cupboards you’re quite often going to find something.”
Cherry said if the weather holds, they’re aiming to have everything done by the end of October.
Highway 11 projects
Cherry said paving has started on the acceleration lanes at Lutheran Road and expect to have traffic on Highway 11 back to normal by the end of the week.
Paving will begin next week on the Corey Road on-ramp. Resurfacing on Highway 305 is slated to begin the following week.
Hwy 16 flyover repairs still a month away says province
By Brent Bosker
Sep 29, 2015 | 11:38 AM
Discover more on CKOM.com
More
Listen Live
On Air Now
8:30 AM - 12:30 PM
Join Evan Bray, the Voice of Saskatchewan, for daily conversations with intriguing guests and fresh perspectives.
NOW TRENDING
OPINION


Murray Wood and a couple of hundred others attended a birthday party on the weekend for a woman who turned 100, and cele...

Sarah Mills: There are echoes of Brexit in the Albert separation issue
A referendum over whether Alberta should separate from Canada is looming closer, and Sarah Mills says there are similari...
LATEST WEATHER
TODAY ON EVAN BRAY


The Evan Bray Show - Tuesday, May 26
8:30 - Canada and the province of Alberta are at a bit of a crossroads. While talks of separatism remain just talks, doe...